August 25, 2020Asheville City Council
From the minutes, not yet reviewedWhat it does
Lets the City Manager execute a Contract Amendment with the John r. McAdams Company Inc. for the Carter-Ann Stormwater Improvements Project -…
- Passed with the routine items, in one vote, without discussion.
- What the minutes say it will do: “The contract amendment will allow The John R. McAdams Company to continue with the design and construction phase of this infrastructure project.”
- The money, in the minutes' words: “Amendment # 1 utilized the contingency and increased the contract amount by $15,500 for a total contract amount of $88,910.”
More from the minutes
- “Eight (8) of the firms submitting qualifications proposed reaching out and utilizing MWBE subcontractors for portions of the project.”
Official title: Resolution authorizing the City Manager to execute a Contract Amendment with the John r. McAdams Company Inc. for the Carter-Ann Stormwater Improvements Project - Contract Amendment 3
Carried unanimously, as part of the consent agenda
From the minutes: This motion was seconded by Councilman Young and carried unanimously by roll call vote.
Read the motion as recorded
“RESOLUTION NO. 20-147 - RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CONTRACT AMENDMENT WITH THE JOHN R. MCADAMS COMPANY INC. FOR THE CARTER-ANN STORMWATER IMPROVEMENTS PROJECT - CONTRACT AMENDMENT 3”
Open the minutesConsent agenda, item P