July 26, 2022Asheville City Council
From the minutes, not yet reviewedWhat it does
Signs a contract with French Broad Paving Inc. for the Sulphur Springs Road Resurfacing project.
- Passed with the routine items, in one vote, without discussion.
- What the minutes say it will do: “The contract is expected to be available on September 15, 2022, and the contractor has until December 15, 2022 to complete the work.”
- The money, in the minutes' words: “7-26-22 Page 4 Action Requested: Adoption of a resolution authorizing the City Manager to execute a contract with French Broad Paving, Inc. in the amount of $501,335.00 plus a 15% contingency of $75,200.25 ($576,535.25 total) for the Sulphur Springs Road Resurfacing Contract.”
- Why it matters: Contracts are how the City pays companies and groups to do work.
More from the minutes
- “The main scope of the project is the resurfacing of Sulphur Springs Road (1.03 miles).”
Official title: Resolution authorizing the City Manager to execute a contract with French Broad Paving Inc. for the Sulphur Springs Road Resurfacing project
Carried unanimously, as part of the consent agenda
From the minutes: This motion was seconded by Councilwoman Kilgore and carried unanimously by roll call vote.
Read the motion as recorded
“RESOLUTION NO. 22-152 - RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CONTRACT WITH FRENCH BROAD PAVING INC. FOR THE SULPHUR SPRINGS ROAD RESURFACING PROJECT”
Open the minutesConsent agenda, item F